Free PMP Exam Sample Question

The following PMP® exam sample question is taken from http://www.free-pm-exam-questions.com – The answer is at the very bottom:

——————————

PMBOK Section: Sequence Activities
Process Group: Planning Process Group
Question Type: Calculation
Knowledge Area: Time Management
Difficulty Level: Moderate

Question: "Activity / Duration / Predecessor

A / 4 / START
B / 3 / A
C / 1 / B
D / 5 / START
E / 4 / D
F / 6 / E
G / 2 / C,F
H / 4 / D
I / 2 / H

What is the duration of the critical path?"

A. 10
B. 11
C. 17
D. 18

Hint : Use PDM to calculate.
Reference: PMBOK4 – pg:138

——————————

All our free questions are updated to the latest PMBOK® Guide standard. Sign up here: http://www.free-pm-exam-questions.com to receive the questions via email. We are a PMI Registered Education Provider.


The answer is C.
Explanation: The duration of the critical path for the given data is 17. Hence choice C is correct while rest of the choices are incorrect.

Comments Disabled

Commenting has been disabled because we are receiving too much spam. Please send your questions & comments to This email address is being protected from spambots. You need JavaScript enabled to view it.

Cornelius Fichtner, PMP

Project manager, PMP trainer, host of The PM Podcast, public speaker and gummi bear addict.