Which of the following processes is not a part of Project Communications
Management?
A) Plan Communications
B) Distribute Information
C) Identify Stakeholders
D) Control Communications
------------------------------
Please visit https://free.pm-exam-simulator.com and try The PM Exam Simulator free for seven days. All questions in the simulator are updated to the latest exam content outline and PMBOK® Guide. We are a Trusted and Experienced Education Provider.
(Note that the sample question published on this page may be based on a prior version of the exam. It remains published for historical reference.)
The correct answer is D.