PMP exam sample questionWhat is a Work Breakdown Structure?

A. A hierarchically-organized depiction of the project organization
B. A hierarchical structure of resource categories
C. It is not part of the project plan
D. A deliverables-oriented decomposition of the project work

 ----------------------

HINT: It illustrates the project scope.

----------------------

Please visit https://free.pm-exam-simulator.com and try The PM Exam Simulator free for seven days. All questions in the simulator are updated to the latest exam content outline and PMBOK® Guide. We are a Trusted and Experienced Education Provider.

(Note that the sample question published on this page may be based on a prior version of the exam. It remains published for historical reference.)

Answer and Explanation:

The correct answer is D.

A work breakdown structure (WBS) is a deliverable-oriented hierarchical decomposition of the work to be executed by the project team to accomplish the project objectives and create the required deliverables.