Free PMP Exam Sample Question

PMP exam sample questionWhich of the following processes does not have Organizational Process Assets as an input?

A. Perform Integrated Change Control
B. Close Project or Phase
C. Collect Requirements
D. Define Activities

-------------------------

Hint: This process is part of project scope management.

-------------------------

Please visit https://free.pm-exam-simulator.com and try The PM Exam Simulator free for seven days. All questions in the simulator are updated to the latest exam content outline and PMBOK® Guide. We are a Trusted and Experienced Education Provider.

(Note that the sample question published on this page may be based on a prior version of the exam. It remains published for historical reference.)

Answer and Explanation:

The correct answer is C.

Collect Requirements has five inputs: The Project Charter, Stakeholder Register, Scope Management Plan, Requirements Management Plan, Stakeholder Management Plan.