Question:question

You have been assigned as the project manager of a highly strategic project which will either make or break your company. It is highly visible and sponsored directly by the Board of Directors who have decided that you need to have maximum control over all project resources. What is the best organization type to use in this case?

A. Weak Matrix
B. PMO
C. Projectized
D. Project Expeditor

-------------------------

Hint: You've got all the control.

-------------------------

Please visit https://free.pm-exam-simulator.com and try The PM Exam Simulator free for seven days. All questions in the simulator are updated to the latest exam content outline and PMBOK® Guide. We are a Trusted and Experienced Education Provider.

(Note that the sample question published on this page may be based on a prior version of the exam. It remains published for historical reference.)

Answer and Explanation:

The Correct Answer is C.

A projectized organization offers the greatest control over project resources for the project manager.