Free PMP Exam Sample Question

Question:question

Your team finished creating the initial version of the Risk Register during your latest workshop. What is the next thing that you should do?

A. Define the probability of occurrence and the impact for each risk
B. Identify the risk effects and assign a numerical rating to each
C. Review cost planning to ensure that enough risk reserve is available
D. Identify, analyze and plan for newly-arisen risks

-------------------------

HINT: You've completed your risk identification.

-------------------------

Please visit https://free.pm-exam-simulator.com and try The PM Exam Simulator free for seven days. All questions in the simulator are updated to the latest exam content outline and PMBOK® Guide. We are a Trusted and Experienced Education Provider.

(Note that the sample question published on this page may be based on a prior version of the exam. It remains published for historical reference.)

Answer and Explanation:

The Correct Answer is A.

The scenario says that you have finished creating the initial version of the Risk Register. Finished means that you have completed identifying risks and prepared the risk register.
Your next step is therefore to move into the Perform Qualitative Risk Analysis process, which is the process where (among other things) you will prioritize risks for further analysis by assessing and combining the probability of occurrence and impact.