Free PMP Exam Sample Question

Question:question

If EV = $100, AC = $90, PV = $110 and BAC = $400, how much is the Cost Variance of a project?

A. $300
B. $40
C. $20
D. $10

-------------------------

HINT: Apply the formula to calculate Cost Variance.

-------------------------

Please visit https://free.pm-exam-simulator.com and try The PM Exam Simulator free for seven days. All questions in the simulator are updated to the latest exam content outline and PMBOK® Guide. We are a Trusted and Experienced Education Provider.

(Note that the sample question published on this page may be based on a prior version of the exam. It remains published for historical reference.)

Answer and Explanation:

The Correct Answer is D.

The formula to calculate Cost Variance (CV) is: CV=EV-AC. Therefore, CV = 100 - 90 = 10.