Question:
A project has the following earned value measurements: EV=100, CPI=1, SV=80. How much is Earned Value?
A. 100
B. 1
C. 1.5
D. 0
-------------------------
HINT: Read the question carefully. The answer is right there.
-------------------------
Please visit https://free.pm-exam-simulator.com and try The PM Exam Simulator free for seven days. All questions in the simulator are updated to the latest exam content outline and PMBOK® Guide. We are a Trusted and Experienced Education Provider.
(Note that the sample question published on this page may be based on a prior version of the exam. It remains published for historical reference.)
Answer and Explanation:
The Correct Answer is A.
The answer is actually in the question. If EV=100, then how much is Earned Value? 100.