On your project you handle known risks by performing the Plan Risk Responses process. Which of the following would you use when you encounter unknown risks?

A.) Risk Reserves
B.) Risk Mitigation
C.) Risk Transfer
D.) Risk Acceptance

------------------------------

Hint: Unknown risks cannot be managed proactively.

------------------------------

Please visit https://free.pm-exam-simulator.com and try The PM Exam Simulator free for seven days. All questions in the simulator are updated to the latest exam content outline and PMBOK® Guide. We are a Trusted and Experienced Education Provider.

(Note that the sample question published on this page may be based on a prior version of the exam. It remains published for historical reference.)

ANSWER AND EXPLANATION:
The correct answer is A
Explanation: Unknown risks are handled by applying Risk Reserves in the project.
Reference: PMBOK® Guide 4th Edition, pages 304, 311