Free PMP Exam Sample Question

The following PMP® exam sample question is taken from the Free PMP Exam Simulator at http://free.pm-exam-simulator.com - The answer is at the very bottom:

 

------------------------------

You developed alternative schedules based on best-case and worst-case scenarios on your project. You want to keep these alternative schedules stored in your project documents, in case of changes in project resources. Where would you store alternative schedules?

A.) Schedule Baseline

B.) Schedule Data

C.) Project documents

D.) Project scope statement

------------------------------

Hint: Alternative schedules are part of one particular output of the Develop Schedule process. Look at those outputs to see where alternative schedules are located.

------------------------------

 

Please visit https://free.pm-exam-simulator.com and try The PM Exam Simulator free for seven days. All questions in the simulator are updated to the latest exam content outline and PMBOK® Guide. We are a Trusted and Experienced Education Provider.

(Note that the sample question published on this page may be based on a prior version of the exam. It remains published for historical reference.)

ANSWER AND EXPLANATION:

The correct answer is B

Explanation: Schedule data is an output of the Develop Schedule process and may contain alternative schedules such as best-case or worst-case scenarios.

Reference: PMBOK4 - pg:159