Free PMP Exam Sample Question

The following PMP® exam sample question is taken from The Free PMP Exam Simulator at http://free.pm-exam-simulator.com - The answer is at the very bottom:

------------------------------

A project manager wants to display and communicate the results of PERT and Critical Path analysis in a simple chart that can be readily understood by those who are not involved in the detail of the project. Which of the following charts should she use?

A) Milestone chart
B) Flow chart
C) Gantt chart
D) Control chart

------------------------------

Please visit https://free.pm-exam-simulator.com and try The PM Exam Simulator free for seven days. All questions in the simulator are updated to the latest exam content outline and PMBOK® Guide. We are a Trusted and Experienced Education Provider.

(Note that the sample question published on this page may be based on a prior version of the exam. It remains published for historical reference.)

The Correct Answer is C.