Free PMP Exam Sample Question

The following PMP® exam sample question is taken from The Free PMP Exam Simulator at http://free.pm-exam-simulator.com - The answer is at the very bottom:

------------------------------

You are the project manager of a project that is in its early phase. You need to estimate the duration of implementing the project. Based on your experience with similar past projects, you estimate a 6-month implementation time. What is this type of estimation technique called?

A) Three Point estimating
B) Bottom-up-estimating
C) WAG
D) Analogous

------------------------------

Please visit https://free.pm-exam-simulator.com and try The PM Exam Simulator free for seven days. All questions in the simulator are updated to the latest exam content outline and PMBOK® Guide. We are a Trusted and Experienced Education Provider.

(Note that the sample question published on this page may be based on a prior version of the exam. It remains published for historical reference.)

The correct answer is D.