The following PMP® exam sample question is taken from The Free PMP Exam Simulator at http://free.pm-exam-simulator.com - The answer is at the very bottom:
------------------------------
You are the project manager of a project that is in its early phase. You need to estimate the duration of implementing the project. Based on your experience with similar past projects, you estimate a 6-month implementation time. What is this type of estimation technique called?
A) Three Point estimating
B) Bottom-up-estimating
C) WAG
D) Analogous
------------------------------
All our questions are updated to the latest PMBOK® Guide standard. Stop by at http://free.pm-exam-simulator.com and try The PMP Exam Simulator free for 3 days. We also offer 110 free questions at http://www.free-pm-exam-questions.com. We are a PMI Registered Education Provider.
The correct answer is D.