Free PMP Exam Sample Question

The following PMP® exam sample question is taken from The Free PMP Exam Simulator at http://free.pm-exam-simulator.com - The answer is at the very bottom:

------------------------------

What is the work breakdown structure (WBS)?

A) It is a deliverable-oriented hierarchical decomposition of the work to be executed by the project team, to accomplish the project objectives and create the required deliverables.

B) It is a hierarchically organized depiction of the project organization arranged so that the work packages can be related to the performing organizational unit.

C) It is a hierarchically organized depiction of the resources by type to be used on the project.

D) It is a hierarchical tabulation of the physical assemblies, sub-assemblies and component needed to fabricate a manufactured product.

------------------------------

Please visit https://free.pm-exam-simulator.com and try The PM Exam Simulator free for seven days. All questions in the simulator are updated to the latest exam content outline and PMBOK® Guide. We are a Trusted and Experienced Education Provider.

(Note that the sample question published on this page may be based on a prior version of the exam. It remains published for historical reference.)

The Correct Answer is A.