Free PMP Exam Sample Question

The following PMP® exam sample question is taken from The Free PMP Exam Simulator at http://free.pm-exam-simulator.com - The answer is at the very bottom:

------------------------------

What is the work breakdown structure (WBS)?

A) It is a deliverable-oriented hierarchical decomposition of the work to be executed by the project team, to accomplish the project objectives and create the required deliverables.

B) It is a hierarchically organized depiction of the project organization arranged so that the work packages can be related to the performing organizational unit.

C) It is a hierarchically organized depiction of the resources by type to be used on the project.

D) It is a hierarchical tabulation of the physical assemblies, sub-assemblies and component needed to fabricate a manufactured product.

------------------------------

All our questions are updated to the latest PMBOK® Guide standard. Stop by at http://free.pm-exam-simulator.com and try The PMP Exam Simulator free for 3 days. We also offer 110 free questions at http://www.free-pm-exam-questions.com. We are a PMI Registered Education Provider.



The Correct Answer is A.

Comments Disabled

Commenting has been disabled because we are receiving too much spam. Please send your questions & comments to This email address is being protected from spambots. You need JavaScript enabled to view it.

Cornelius Fichtner, PMP

Project manager, PMP trainer, host of The PM Podcast, public speaker and gummi bear addict.