Free PMP Exam Sample Question
The following PMP® exam sample question is taken from The Free PMP Exam Simulator at http://free.pm-exam-simulator.com - The answer is at the very bottom:
------------------------------
What is the work breakdown structure (WBS)?
A) It is a deliverable-oriented hierarchical decomposition of the work to be executed by the project team, to accomplish the project objectives and create the required deliverables.
B) It is a hierarchically organized depiction of the project organization arranged so that the work packages can be related to the performing organizational unit.
C) It is a hierarchically organized depiction of the resources by type to be used on the project.
D) It is a hierarchical tabulation of the physical assemblies, sub-assemblies and component needed to fabricate a manufactured product.
------------------------------
All our questions are updated to the latest PMBOK® Guide standard. Stop by at http://free.pm-exam-simulator.com and try The PMP Exam Simulator free for 3 days. We also offer 110 free questions at http://www.free-pm-exam-questions.com. We are a PMI Registered Education Provider.
The Correct Answer is A.