The method of constructing a project schedule network diagram that represents activities and connects them to show the dependencies is known as:
A) Arrow diagramming method
B) Schedule network templates
C) Precedence diagramming method
D) Activity list
------------------------------
All our questions are updated to the latest PMBOK® Guide standard. Stop by at http://free.pm-exam-simulator.com and try it for 3 days. We are a PMI Registered Education Provider.
The Correct Answer is C.