The method of constructing a project schedule network diagram that represents activities and connects them to show the dependencies is known as:

A) Arrow diagramming method
B) Schedule network templates
C) Precedence diagramming method
D) Activity list

Please visit https://free.pm-exam-simulator.com and try The PM Exam Simulator free for seven days. All questions in the simulator are updated to the latest exam content outline and PMBOK® Guide. We are a Trusted and Experienced Education Provider.

(Note that the sample question published on this page may be based on a prior version of the exam. It remains published for historical reference.)

The Correct Answer is C.