Free PMP Exam Sample Question

Free PMP Exam Sample QuestionQuestion:

You have been assigned as the project manager for an upcoming telecommunications project in a developing country. Due to cost issues, you cannot take the entire project team from your local country to the country where the project will be executed. You take a few of the project team members with you and plan to hire the rest of the team from the local job market. You are also considering building a virtual team to get technical support from the country of your origin. Which of the following problems are you likely to face as a result of having a virtual team?

A. Virtual team members lack motivation
B. The use of a virtual team may create noise
C. Virtual team members cannot communicate frequently
D. Technical assistance cannot be provided by the virtual team members

-------------------------

Hint: Virtual teams are groups of people with a shared goal who fulfill their roles with little or no time spent meeting face-to-face.

-------------------------

All our questions are updated to the latest PMBOK® Guide standard. Stop by at http://free.pm-exam-simulator.com and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at http://www.free-pm-exam-questions.com. We are a PMI Registered Education Provider.

Answer and Explanation:

The Correct Answer is B.

The use of virtual teams creates new possibilities when acquiring project team members. Virtual teams can be defined as groups of people with a shared goal who fulfill their roles with little or no time spent meeting face-to-face. The availability of electronic communication such as e-mail, audio conferencing, web-based meetings, and video conferencing has made such teams feasible. Noise is anything that interferes with the transmission and understanding of the message (e.g. distance, unfamiliar technology, lack of background information, etc.). Noise is the biggest concern for virtual teams.

 