Free PMP Exam Sample Question

 

Question:QandA11

What percentage of their time do project managers spend communicating?

A. At least 25%
B. No more than 75%
C. 80%
D. 90%

-------------------------

Hint: It's a lot!

-------------------------

All our questions are updated to the latest PMBOK® Guide standard. Stop by at http://free.pm-exam-simulator.com and try the PMP Exam Simulator free for 3 days. We also offer 110 free questions at http://www.free-pm-exam-questions.com. We are a PMI Registered Education Provider.

Answer and Explanation:

The Correct Answer is D.

According to Kerzner, project managers spend 90% of their time communicating.

 

Print Email